EIA report: California hydroelectric facilities continue to respond to prices despite drought
Despite widespread, intense drought conditions, hydroelectric power plants in the California Independent System Operator (CAISO), the grid operator for most of the state, provided a significant amount of generation from April 2021 to September 2021, according to the U.S. Energy Information Administration.
Although drought conditions reduced water supply, hydroelectric generation during this period still increased in response to the higher average hourly electricity prices in the late afternoon.
So far in 2021, monthly generation from hydroelectric plants in California has been near the bottom of its 10-year range. To maximize revenue, hydroelectric plants must concentrate their generation into the hours of the day when electricity demand — and, therefore, prices — are highest, typically between 6:00 p.m. and 9:00 p.m.
Hydroelectric generators provided an average of 5% of the total generation in CAISO from April 2021 to September 2021. During the peak-priced hour, however, that share jumped to 10% of total generation, making hydro the third-largest source of electricity after natural gas and electricity imports from other grid operators in California and out of state. Price data are based on the day-ahead electricity price for the NP-15 generation pricing hub in Northern California, where most of the state’s hydroelectric capacity is located.
Hydroelectric plants are subject to regulatory, environmental and recreational requirements, as well as physical storage limitations and the interconnected nature of operating units within a watershed. The impact of these constraints on hydroelectric generation is increased by the sustained drought, which limits the availability of water. To conserve limited water resources for use during the highest-priced hours of the day, hydropower plants submit economic bids, or schedules, to generate in California’s wholesale electric market.
Hydroelectric generation varies significantly by day and by hour. From April 2021 to September 2021, daily output from hydroelectric plants in CAISO averaged over 30,000 MWh per day, ranging from a low of nearly 15,000 MWh to a high of more than 52,000 MWh. The maximum hourly hydroelectric generation each day ranged from more than 2,000 MWh to over 4,500 MWh. As a result of limited water availability, the maximum output level can only be sustained for one or two hours per day.
Hydroelectric generation includes generation from pumped storage power plants, EIA said.
Source: Renewable Energy